Factory Island Substation Upgrades

As part of our commitment to provide safe, resilient service to our customers, we are preparing to upgrade the substation located at 109 Main Street on Factory Island in Saco. We are working with communities and reaching out to neighbors to ensure that all improvements are performed safely and with minimal disruptions to their daily lives, the community, and the environment.

project scope and need factory island

Enhancing reliability through infrastructure upgrades

 

The project scope includes replacement of two existing transformers with upgraded transformers that will increase system capacity and redundancy, new circuit breakers, updated smart communications devices, and a new battery bank to improve reliability and resiliency.

The purpose of this project is to upgrade the existing substation due to its age and potential inability to meet load requirements and the growing needs of the area. The new substation will improve the reliability of service forover 7,600 area customers and provide increased capacity to support future growth.

 

Benefits to our customers

Publicador de contenidos

Increased power capacity

The upgraded substation's increased capacity will help meet the electricity needs of customers.

The upgraded substation's increased capacity will help meet the electricity needs of customers.

Improved reliability & resiliency

These upgrades will improve the reliability and resiliency of our system, improving service for our customers. 

These upgrades will improve the reliability and resiliency of our system, improving service for over 2,300 customers. 

Support for future growth

Built with tomorrow in mind, this project helps customers stay ahead as demand increases.

Publicador de contenidos

Contact us

project facts and timetable and work hours factory island

More information

 

Project facts

  • Municipality: Saco
  • County: York
  • Permitting Required: City of Saco Planning Board Review, Saco River Corridor Commission, ME Dept. of Environmental Protection

Estimated timetable

  • Construction: Summer 2025

  • Estimated Completion: Fall 2026

Work hours and impacts

Work activity periods will comply with city ordinances. Work will be conducted during daylight hours, utilizing existing access points, and will entail the use of heavy machinery. As a result, nearby property owners may experience:

  • Traffic disruptions, including the use of flaggers and temporary lane closures.
  • Typicalconstruction noise, including backup beeping, should be expected.Abuttersmay hearthe use ofheavy equipmentvehicles (bucket trucks,drilling equipment).